WTC Construction Update, October 2010
Wednesday, November 10, 2010
World Trade Center Construction Update, October 2010
New York, October 22, 2010
Memorial and Museum
-More than 40,000 cubic yards of concrete poured
-Steel erection is 99% completed
4 World Trade Center
-Concrete poured to the 4th floor
-Framed deck up to the 6th floor
-Installed steel up to the 7th floor
3 World Trade Center
-200 cubic yards of concrete to be poured in footings this month
2 World Trade Center
-1540 cubic yards of concrete to be poured in footings this month
1 World Trade Center
-Installed steel to the 38th floor
-Concrete poured up to the 32nd floor
source: wtc.com